SOUTH BANK TOWER Contractor: Mace Architect: KPF Value: £14m Engineer: AKT Temporary works design development Installation of temporary works and high level crash decks Progressive demolition Install temporary works to support the 11th floor structure Demolish and infill works, to areas affecting the new construction De-construct west stair core progressively down to basement New construction of core progressively up from basement to 10th floor Remaining demolition and infill works